Whakatane Mill Winder Support

Background

In the paper industry, the winder area is a collection of motors and drums used to wind large production rolls of paper or cardboard onto smaller, more manageable-sized rolls. It plays a crucial role in the post-manufacturing process by resizing the wide rolls produced by the paper machine into smaller, narrower rolls. These rolls are suitable for various end uses, such as printing or packaging, depending on the client’s needs. The winder area includes rolls for unwinding, slitters, and roll-handling equipment.

WML needed to increase production at their Whakatāne plant after the Smurfit Consortium purchased the Mill in 2021, along with the planned upgrade project. Mainstream Engineering was awarded the contract to design and manage the upgrade process and brought Tiaki on board for the Civil, Structural, and (limited) architectural elements. The project started in early 2022, with foundation concepts being developed for feasibility and estimation purposes.

August 2022 saw the first stages of detailed design emerging, followed by on-site construction facilitation and “live” line modifications where possible, in early 2023. This culminated in the machine line shut and equipment install from July 2023. After the successful commissioning of the plant, the first “new” roll reached the winder in mid-September.

Objectives and Constraints

The construction timeline was very tight, as the plant shut was envisaged to last only 4-6 weeks. The design had to be carefully considered, with the aim to build as much supporting structure without interrupting paper production prior to the shut. This greatly reduced the work to be done during the shut.

The winder machine itself was supported on 800 mm concrete foundation walls and a 2 x 2 m concrete perimeter pile cap founded on 48 x 10 m deep screw piles over a plan area of 17.8 x 8 m. To reduce construction times, especially limiting the amount of concrete that needed to be poured (and cured) during the shut, the surrounding operational floor was designed to be part concrete and part pre-manufactured steel.

Project Outcomes

By the end of the shut, the project was completed, with some minor additional work required for its finalisation. This did not, however, come without some serious engineering input during the process—the combination of a tight timeline and an equally tight workspace produced some interesting challenges. These were collaboratively solved by the contractors, the mechanical engineers, and the machine installers.

Of the challenges faced, the biggest one to overcome was the intricate staging of the works for the area’s timely access by the next trade to install the machinery. Solutions included the use of high-strength concrete to accelerate concrete strength gain to achieve design values within the shut, post-installed anchors to facilitate install, and oversizing of holes in steel plates. To anticipate potential clashes and ensure construction tolerances, as-builts were updated throughout construction.

tiaki donald
Donald Richardson
Project Manager
Project Details
Type of workDesign / Management
Project name:Whakatāne Mill Winder Support Structure
Client:Whakatāne Mill Limited (WML)
Department:Civil / Structures
Physical Address:Coastlands, Whakatāne
Total Project Budget:2.2 Million
Final Cost of TECL Work:200k
Commencement:January 2023
Project Partners:MEL

Contact Us

Get In Touch

Our breadth of specialised knowledge has allowed us to provide and oversee unique and practical design solutions for a wide range of projects across the North Island, and as far as Scott Base, Antarctica.

Let’s discuss what Tiaki Engineering Consulting can do for your civil, geotechnical or structural engineering project.

Email Us

Email TECL directly and we’ll forward your enquiry to the most appropriate person.

Email Us

Email TECL directly and we’ll forward your enquiry to the most appropriate person.

Call Us

Prefer to speak over the phone? Let’s talk.

Call Us

Prefer to speak over the phone? Let’s talk.